111 _aJoint meeting for support to special Public Works programmes.
111 _d13-15 April 1983
245 _aEvaluation of the Dominica special work programme related to reconstruction: a summary of findings and recommendations.
300 _a5 p.
500 _aCentre has two (2) copies
520 _aRecords progress made under the project. Notes weakness of project, including limited staff, emergency character of the project, the lack of contingencies to offset the Dominican terrain and climate. Recommends new arrangements for disbursement of funds, revision of cost estimates, provision for operation and operation of vehicles among others.
556 _aGeneral
650 _aROAD
650 _aFORESTRY
650 _aWOODWORKING INDUSTRY
650 _aDOMINICA
650 _aPROJECT EVALUATION
650 _aAGRICULTURE